4D Sequencing Simulator

Link the model to the programme and press play. Watch the build rise week by week, from excavation through substructure, superstructure, envelope and fitout, with a live Gantt tracking each phase, the same 4D sequencing we deliver in Synchro and Navisworks.

Published

What this demonstrates

4D sequencing and BIM automation. The 4D pipeline we deliver in Synchro and Navisworks, exposed here as a scrubbable programme linked to a live model.

Wk 9 / 22·57%

Programme (4D)

Week 9 of 22

Where this data comes from

Illustrative pipeline for a production deployment

Federated model (Revit / Navisworks)

Structure, envelope and services elements to sequence

Construction programme (P6 / MS Project)

Tasks, durations and logic links

Zoning & work breakdown

Element-to-task mapping rules by zone and level

4D link (Synchro / Navisworks)

  1. 1Map model elements to programme tasks
  2. 2Attach appearance profiles per activity
  3. 3Play the sequence and test constructability
  4. 4Publish 4D reviews and look-aheads

Output

4D construction model

A time-linked model for sequence reviews, logistics and high-risk activity rehearsal

Progress

57%

Week 9 of 22

Phases (click to toggle)

Active this week

Level 2 structure

Task windows and progress at the current week.

FAQ

Frequently asked questions

How these demos relate to the systems we build for clients.

What is 4D construction sequencing?

Linking the 3D model to the construction programme so the build plays back over time. Each task drives the elements it delivers, so you can see the structure rise week by week, rehearse high-risk activities and test whether the sequence is actually buildable before anyone is on site.

Is this a real programme?

The tasks and durations here are a synthetic illustration. In client work the sequence is linked to the real programme in Synchro or Navisworks, with tasks mapped to model elements so the 4D stays in step with the master schedule.

How does this help on accelerated builds?

Data centre and infrastructure programmes are compressed and coordination-heavy. A 4D model exposes clashes in time as well as space, checks crane and laydown logistics against the sequence, and gives everyone a shared, visual understanding of the plan.

Can it produce a schedule?

Yes. The phase schedule here exports to PDF with each task's window and current progress. Production 4D links directly to the programme file so the model and the schedule are never out of sync.